MAJOR MILESTONES

  • Tower deck pour complete (Level 17)

  • Podium deck pour complete (Level 1)

  • Self-climbing tower core formwork is ongoing

  • Structural steel at elevator shafts & stairs is ongoing

  • Interior framing at residential floor complete (Level 9)

  • MEP risers at residential floor complete (Level 11)

  • LASAN sewer work off 8th St. & Francisco St. is ongoing during the hours of 9PM-4AM

  • Early TCO awarded for the P6 Pedestrian Tunnel (connects FigAt7th &Parking Structure)

  • Backfill operation between new and existing structures resumed (on-going)

  • Removal of shoring piles off 8th Street started on 7/28 (3-week duration) - Additional Lane closures to take place when this activity is concurrent with concrete pours

SCHEDULED ACTIVITIES

  • Tower deck forming, reinforcing, and pouring (Level 18-22)

  • Podium deck forming, reinforcing, and pouring (Level 2)

  • Core wall rebar & concrete activities (Level 23-27)

  • Interior framing at residential floor (Level 12)

  • Window Wall installation (Level 5-6)

TO OUR NEIGHBORS

Structural concrete operations are ongoing at the 960 W 7th Street site located between the FIGat7th parking structure and 777 Tower.

It is our priority to communicate with our neighbors, and to the best of our ability, minimize the impact our construction activities may have on you, while maintaining a safe environment for the public and construction team, alike. 

To this end, we would like to share the following information about our construction-related activities:

  • The project is in compliance with CDC, OSHA, and City of Los Angeles guidelines concerning COVID-19 mitigation measures for Essential businesses.

  • Access to driveways on 8th Street will be maintained at all times. 

  • The two northern lanes on 8th Street in front of the project will be closed during Phase II of construction, as approved by LADOT.

  • Pedestrian access on 8th Street, in front of the project, will be maintained. 

  • The Occupational Safety and Health Administration (OSHA) requires all trucks and equipment (such as forklifts) to have audible backup alarms. Additionally, the tower crane operators are required to sound their horn when hoisting a load overhead. 

  • Normal working hours: M-F: 7 am to 9 pm / Sat: 8 am to 6 pm

  • Approved extended work hours for soil export from 9 pm to 6 am

  • Approved extended work hours for concrete activities from 4am to 7am and 9pm to 11pm Monday - Friday